Fulton Hogan has applied for a full road closure between Ben Avon Grove and the light house end of Cape Palliser Road from Monday 7 April until Wednesday 16 April.
The work (RP 34587) was originally forecast to be completed on Monday 14 April but a two day extension has now been sought by the contractor to ensure the workers can repair the ford in the road, as pictured below.
There will not be any work over the weekend but the closure will remain in place 24/7 to allow the concrete to cure.
Notes on the ford repair
- There is no detour available for the duration of the work
- Pedestrian access is available
- Parking access is available
- Signage will be in place