Featherston Watermain Renewal | Night works on Sun 21 Jun

Our thanks to the Featherston community as we’ve been steadily working towards completing our Featherston Watermain Renewal project.

We have one more night of works scheduled for Sunday 21 June, and then it’s back into daytime work.

The work over the last few days has gone well with Revans Street connections completed. Next week we are doing reinstatement works and some valve testing around Fitzherbert Street (east). When we test valves there can be small interruptions to water service of a minute or two.

Date of worksLocation and work to be completedScheduled works
Sunday 21 June – Night, 7pm-5amRevans St and Wakefield St – Road crossingAsphalt reinstatement areas
Tuesday 23 JuneFitzherbert St East bridgeReinstatement
Wednesday 24 JuneFitzherbert St EastInvestigation work
Thursday 25 JuneFitzherbert St EastInvestigation work
Friday 26 JuneFitzherbert St EastReinstatement and tidy up

Find out more about the project: Featherston Watermain Renewals – 2025/26 – SWDC