Wastewater Treatment Plant upgrades project
Martinborough, Featherston and Greytown
Council’s 2025-34 Long-Term Plan includes significant upgrades to the wastewater treatment plants in Martinborough, Featherston and Greytown. These upgrades are part of the Council’s commitment to improving water management and infrastructure. The decision was made to manage capital infrastructure in-house until the new water services entity Waitī Waters is established on 1 July 2027. With a focus on cost control and efficiency, the Wastewater Treatment Plant (WWTP) upgrades project is part of implementing this strategic direction.
About this project
The WWTP upgrades project is essential for the sustainable growth aspirations of South Wairarapa communities. All three wastewater treatment plants need treatment process upgrades to address the regulatory requirements and consent conditions for each site.
The Council has worked closely with Greater Wellington Regional Council to agree to achievable and technically proven enhancements to improve environmental and technical performance.
Upgrades
The WWTP upgrades project will deliver the following:
- Martinborough and Greytown wastewater treatment plants will have Moving Bed Biofilm Reactors (MBBR) installed as the primary process for nutrient removal and Greytown wastewater treatment plant will also have an upgraded UV disinfection system to reduce pathogen risk.
- In accordance with the consent at Featherston Wastewater Treatment Plant, a Dissolved Air Floatation (DAF) system will be installed for nutrient removal. The DAF removes solids and phosphorous improving the performance of the existing oxidation ponds as the primary biological process.
- All three treatment plants will have inlet screen upgrades to remove solids that clog up equipment. Additionally, there will be associated upgrades of power supplies and control systems for the new equipment.
Timeline
The project is scheduled for completion within the 2027/28 financial year, which means that project completion will be under the banner of Waitī Waters, Wairarapa–Tararua’s new regional water services organisation.
Martinborough Wastewater Treatment Plant Upgrade Project
November 2026 to August 2027
About this project
The Martinborough Wastewater Treatment Plant (WWTP) Upgrade project is the first of three programmed wastewater treatment plant capital upgrade projects, with construction works beginning mid-November and scheduled for completion by the end of August 2027.
Project management
Following a rigorous tender evaluation process, Filtec Limited was engaged in July 2026. Filtec are the principal contractor and have demonstrated strong capability in delivering comparable wastewater treatment upgrades at operational plants. Pope & Gray Contractors will carry out the civil works. South Wairarapa, Filtec Limited, Pope & Gray Contractors and GHD Limited will deliver the project as one team.
What is being built
The upgrade adds new treatment equipment next to the existing wastewater treatment ponds. This work will be completed as the existing wastewater treatment plant continues to operate under the oversight of Citycare Limited.
- A raised, engineered platform about 2m above existing ground, so the new equipment sits above flood level
- Two new treatment tanks on concrete foundations
- Two small buildings: a blower building and an electrical room
- A new inlet screen at the main inlet pipe from the network
- UV disinfection upgrades and a new chemical storage/dosing system, with new pipework, a pump station and a power supply upgrade.


Programme
The programme dates below are from the current construction programme, any changes will be updated as required.
| When | What is happening | What you will notice |
| 9 November 2026 | Site establishment – site set-up, fencing, signage, erosion and sediment controls | Daily light vehicles for construction staff, plus four to five truck deliveries of machinery |
| Mid-November to mid-December | Earthworks: topsoil strip, ground improvement and filling the platform For public health and safety, the Palliser Vineyard Walk will be closed to the public from 9 November until the Christmas break on 23 December | This is the busiest period with truck and trailer units carting fill. There will be up to 20 heavy vehicle movements a day. Public signage will be on display advising no public access onto Palliser Estate via the Weld Street entrance. |
| 23 December 2026 to 5 January 2027 | Christmas break | No site activity Palliser Vineyard Walk open again |
| January to February 2027 | Pipework and services, tank foundations installation | Fewer trucks, primarily concrete trucks and material deliveries |
| February to April 2027 | Tanks, buildings and inlet-screen installed; mechanical installation | Scheduled large deliveries – includes a crane or HIAB on some days |
| May to June 2027 | Electrical completion, commissioning and testing | Little traffic, mainly daily light vehicles for construction staff |
| June to August 2027 | Final outstanding work | Little traffic. Works planned for completion by the end of August 2027. |
Working hours
Monday to Friday from 7am to 6pm and Saturday to 2pm. No Sunday work unless unexpected delays occur during earthworks. Please note that some extended hours may be needed before the Christmas break to finish the ground improvement. If this is the case, neighbours will be advised in advance and the community advised via social media.
Traffic and access
All construction traffic uses the existing access road through Palliser Estate. About 2,600 m³ of fill will be brought in, roughly 130 truck-and-trailer loads, mostly between mid-November and mid-December. This means that the Palliser Vineyard Walk will be closed to this live construction site from 9 November to 23 December 2026 for health and safety reasons.
The route that the truck-and-trailer loads will take into the residential area is shown below.

After the Christmas break, traffic drops to material deliveries and a small number of scheduled large deliveries.
Featherston Wastewater Treatment Plant Upgrade Project
March 2027 to November 2027
About this project
The Featherston Wastewater Treatment Plant (WWTP) Upgrade project involves the installation of a Dissolved Air Floatation (DAF) system for improved clarity of treated wastewater and improved disinfection performance, in addition a new inlet screen will be installed, together with upgraded control systems and power supply upgrades.
This upgrade is a resource consent requirement. The DAF was selected as the most affordable upgrade to significantly reduce suspended solids, improve effluent quality and UV performance, and address the key environmental issue of sediment impacts on Donalds Creek.
Detailed design for this project will be undertaken in early 2027, with construction scheduled to begin in March. The project is expected to take approximately seven to eight months to complete.
Greytown Wastewater Treatment Plant Upgrade Project
August 2027 to April 2028
About this project
As in Martinborough, the Greytown Wastewater Treatment Plant will have Moving Bed Biofilm Reactors (MBBR) installed as the primary process for nutrient removal. Detailed design for this project will be in early 2027 and construction works are scheduled to begin mid-2027 in August with practical works completion in early 2028.