Featherston Watermain Renewal project update | Night works, 7-11 June

The Featherston Watermain Renewal project is in its final few weeks to completion at the end of this month.

Thank you to the Featherston community for your ongoing patience with the disruption caused in our watermain pipe laying work.

The last period of scheduled night works generated some noise disturbance concerns. In response, we have re-considered the works programme to identify all opportunities to minimise disruption to the Featherston community. This includes ensuring that loud noise generating machines stop operating by 8pm to ensure comfortable compliance with noise control standards.

Night works are necessary to complete our work particularly on Fitzherbert Street SH2, to meet traffic management planning requirements.

Working between 7pm and 5am will ensure less impact to the commercial area, road users, and pedestrians, and also less impact to public transport. Traffic staff will be onsite to manage the traffic flows and the pedestrians to ensure that they all pass the worksite safely.

This approach maintains continuous traffic flow, avoids long traffic queues and delay, and minimises the overall impact on the traffic network.

The dates and locations of scheduled night works for the next five working days are shown below.

Works at a glance

  • Hours of operation are between 7pm-5am
  • Noise control: Compliant with NZS6803 – any cutting work to be completed prior to 8pm
  • Night works schedule
Date of night worksLocation and work to be completedScheduled works
Sunday 7/6/26Lyon St Complete – connections
Monday 8/6/26Revans StComplete mains installation
Tuesday 9/6/26Fitzherbert St and Revans StReinstatement
Wednesday 10/6/26Fitzherbert St and Revans StReinstatement
Thursday 11/6/26Fitzherbert StReinstatement

Find out more about the project: Featherston Watermain Renewals – 2025/26 – SWDC